United Utilities has launched market engagement for a design and integration role potentially worth up to £600m on its proposed Windermere wastewater overhaul.
The initial four-year phase was valued at £60m-£100m, with optional construction-phase roles worth £100m for system integration or £500m including detailed design.
The delivery roles were alternatives, rather than cumulative, and United Utilities said it could choose a different partner after the initial phase.
The preliminary notice, published on 21 October, values the design and integration role at £720m including VAT.
Its release coincided with a feasibility study valuing the wider wastewater programme at £3.6bn-£3.7bn.
A coalition including United Utilities assessed more than 70 possible solutions before identifying two preferred options, both involving transferring wastewater away from the lake for advanced treatment.
The proposals include a new wastewater tunnel, up to 138km of sewerage network, 35km of highway runoff interception and 37 hectares of sustainable drainage.
Around 12,800 people could be connected to public sewers for the first time, while wastewater infrastructure across the catchment could increase by up to 75 per cent.
The coalition envisages a seven-year construction programme following detailed design, planning and regulatory approvals.
Under the proposed procurement, the design and integration partner would be responsible for developing outline designs, assessing constructability and coordinating the various infrastructure workstreams.
Its responsibilities would also include ground investigations, environmental assessments, land acquisition support and preparing and submitting planning applications.
United Utilities anticipates seeking a development consent order (DCO) for the programme under the Nationally Significant Infrastructure Project regime, subject to Section 35 approval from Defra.
The partner would be responsible for preparing and submitting the DCO and coordinating early contractor involvement ahead of construction.
The proposed framework was expected to begin in April 2027 and run until March 2031, with possible extensions taking it to March 2040.
United Utilities invited prospective suppliers to a virtual programme launch event on 29 October, with registration closing on 27 October.
A formal tender notice was provisionally scheduled for publication on 5 November.
United Utilities stressed that its preliminary market-engagement notice did not constitute a call for competition or commit it to proceeding with the procurement.