MHI booked 8 GW of large frame gas turbine orders in the first half of its fiscal 2026, compared with 16 GW for all of fiscal 2025, and its large frame backlog stands at 37 GW. Orders in its Energy Systems segment, which includes gas turbines, nuclear power and aero engines, rose 16% from a year earlier, and segment profit rose 80%, helped by more orders and exchange rates [1].
Ito expects global gas turbine demand to average about 70 GW a year over the next five years and called the roughly 100 GW of sales expected across manufacturers in 2026 “exceptionally strong” demand that he does not expect to last. MHI is spending about $3.1 billion to add gas turbine manufacturing capacity and plans to double production capacity by 2030, mostly through process improvements and automation at existing plants in the U.S. and Japan [1].
MLQ.ai earlier covered Venture Global’s pitch of 5 GW of off-grid power for AI data centers.